London Islamic Centre

Extensive refurbishment and full re-design of Phase 1A basement and ground floor leading to the refurbishment of levels 1 & 2

Type – Refurbishment and fit out
Project Value – £1.5M 
Duration – 21 Weeks

The London Islamic Centre phase 1a of this project is now complete, this site will eventually lead to the completion of a 5000-capacity mosque. This will result in one of the largest prayer capacities in London.

The project for Phase 1A was initially for 21 weeks with additional variations to suit the most up to date fire strategy regulations, such as smoke extraction and a sprinkler system. Daniel Lines is the Project Manager and it has been running with up to 30 operatives daily. The project involves the full refurbishment and mechanical and electrical package of Phase 1A basement and ground floor. The project total currently stands at £1.5m. This first phase of the project will eventually lead to the refurbishment of levels 1 & 2 with a mechanical and electrical package also.