Woodlands Primary School

Our works included a full Electrical rewire, full mechanical upgrade with brand new plant room, asbestos removal, decorations and making good.

Type – Planned preventive maintenance program (PPM)
Project Value – £800k
Duration – 16 weeks

This project at Woodlands Primary School in Ilford was successfully awarded to Longley via competitive tender bid as part of the planned preventive maintenance program (PPM), which commenced in November 2020.

Our Mechanical and Electrical works included the replacement boiler plant room, heating distribution system upgrades to the sports building, boiler flue installation, new BMS panel, control wiring to the sports hall plant room, upgrading all electrical systems, components and light fittings, as well as replacing all power and lighting to the Design and Technology block and sub mains and cabling throughout.

Our builders works included asbestos removal, brand new suspended ceilings, decorations and making good.

Reuben Skidmore managed this 16-week project valued at £800,000 together with Consultant Project Lead Michael Perschky and Technical Consultant Scott Tillsley from Ingleton Wood with Redbridge Council’s Project Lead Shamim Ahmed. Our extensive and diverse industry knowledge and consciousness of our clients’ and end consumer’s needs, The Longley Group has been entrusted to work in over 100 schools, this trust comes from our ability to assess situations and pre-determine outcomes. Being a diverse company sets the Longley Group apart by providing innovative solutions to problems when they arise without compromising on program, quality or safety.